13.12.620 – Reports of changed conditions

Each User shall notify the Director of Public Works of any planned significant changes to the User's operations or system which might alter the nature, character, or volume of its wastewater at least thirty (30) days before the change.

  1. The Director of Public Works may require the User to submit such information as may be deemed necessary to evaluate the changed condition, including the submission of a wastewater discharge permit application under Section 13.12.540.
  2. The Director of Public Works may issue a wastewater discharge permit under Section 13.12.570 or modify an existing wastewater discharge permit under Section 13.12.580 in response to changed conditions or anticipated changed conditions.
  3. For purposes of this requirement, significant changes include, but are not limited to, flow increases of twenty percent (20%) or greater, and the discharge of any previously unreported pollutants.